Site
Hampstead VFC Operational Fund


Upcoming Events

There are currently no events
2024 Responses
Fire EMS
Jan 60 124
Feb 59 132
Mar 55 140
Apr 61 125
May 49 119
Jun 55 133
Jul 58 129
Aug 53 130
Sep 60 132
Oct 46 113
Nov 59 96
Dec
Total 615 1373

2023 Responses
Fire EMS
Jan 58 155
Feb 49 149
Mar 54 131
Apr 61 124
May 49 133
Jun 81 136
Jul 69 141
Aug 71 110
Sep 49 114
Oct 55 130
Nov 67 131
Dec 54 145
Total 717 1599

Past Responses
Fire EMS
2022 673 1500
2021 604 1440
2020 554 1143
2019 537 1208
2018 551 1390
2017 792 1454
2016 719 1397
2015 812 1410
2014 752 1288
2013 608 1251

Web Counters
Website Visitors
Since
January 1, 2019
4,147,111
Visitors Today
Dec 21, 2024
424

HAMPSTEAD VFC BUILDING PROJECTS

 

 

 

 

 

 

  

Visit Capital Campaign Donation Page

 

 

Time Lapse Construction Progress

 

Time Lapse Demolition of Existing Station

Week of August 12, 2023 -  7/21/23 Footers poured, 7/28/23 Northeast 2 story wall construction begins, 8/4/23 North East 2 story wall has been completed, 8/11/23 Front and rear 2 story wall construction begins. We are excited to see the progress, as our site continues to change on a daily basis. 

Stay tuned for more updates.

  Interior photo   

Week of July 19,2023 -  Site work continues underground water line has been installed and footers for the foundation have been poured.

Stay tuned for more updates.

  Interior photo   

May / June 2023-  During the month of May & June contractors worked on stripping and demolishing the old station to prepare for the site work for the new station. The site has been cleared and prepped for the new foundation.

Stay tuned for more updates.

  Interior photo   

April 2023-  Photo 1: The entrance to the old station was closed for demolition (4/4/23)

Photo 2: In preparation for the demolition, Chief Hipsley removed the cornerstone from the old station. There was no vault behind the cornerstone with any artifacts. (4/7/23)

Photo 3: Appartus Bay of the temporary station (4/7/23)

Photo 4: Memorial in front of the old station was removed. All of the stone was carefully removed and will be stored so that the stone can be incorporated into a new memorial wall at the new station. The metal letters on the front of the station were also removed and are in the procedd of being restored by Shannon-Baum Signs to incorporate them as well in the new station memorial. (4/20/23)

Stay tuned for more updates.

  Interior photo   

March 2023-  We have started to hang some finishes in our temporary station so it feels like home. In the first photo you will see our station logo thoughout the years (3/19/23)

Photo 2: Our exterior signage was installed by Shannon-Baum Signs (Eldersburg, MD) 3/21/23

Photo 3: Our exterior canopy was installed 3/22/23

Photo 4,5: Exterior lighting was installed 3/29/23

Photo 6: All inspections have passed and we received our use and occupancy permit. We have officially switched our emergency operations to the temporary building so the new station can be built.

Stay tuned for more updates.

Event Center Apron Install 12/2/22    Overhead exterior lighting Move-in date 3/31/23

February 2023-  All interior work has been completed. We are waiting on some backordered electrical parts so that permanent power can be connected and we can obtain our use and occupancy permit.

 Stay tuned for more updates.

     

January 2023-  All work has been switched to interior fit out. On the exterior, we completed the concrete driveway in between the buildings and the rear retaining wall. While driving by it will not look like much progress but rest assured that we are progressing towards our new expected move in date of March 31, 2023.

 Stay tuned for more updates.

Concrete driveway between bldg Rear retaining wall installation 1/20/23    

Week of 12/02/22-  We have accomplished a lot over the last 45 days – We have gotten the interior block wall in, all of the metal framing walls, and interior plumbing and HVAC duct work. The HVAC unit was placed. The front apron was completed along with the trench drains. The Storm water bio retention pond have been installed along with all of its components and tied into the town storm drain. The retaining wall, and fence have been installed and this week the guard rail will be installed in the alley. The generator pad has been installed and the transformer pad and sidewalks are being installed in the next week. The bay doors have been installed and we have temporary heat in the building.

 We expect to occupy the temporary/interim station by March 15, 2023 and expect the current station to be torn down in the first part of April 2023 to begin the Phase 2 process of building the new fire station in its place.

 

This week the parking lot upper and lower will be blacktopped by White Pine Paving a local contractor.

 

Stay tuned for more updates as we finish up our civil exterior work before the first snow.

Event Center Apron Install 12/2/22 Bay door install 12/2/22 Event Center Interior block wall 12/2/22 Overhead site 12/2/22 Rear site 12/2/22 Site overhead Main St. 12/2/22

Week of 10/17/22-  A lot of work took place this week. The retaining wall was constructed, the fence, guardrail and final grading stilll needs to be done. The electric duct bank, fiber, Verizon and Comcast duct bank was installed. The water line to the pit beef building was installed and the framing of the entrance was completed.

Site overview 10/18/22 concrete floor installation duct bank installation utility duct bank install retaining wall install pit beef water line install

Week of 9/23/22- Keystone has been installing the roof and insultation which is now completed and they are beginning to work on the side walls and Insulation.  

Roof Install roof install water line install Site overhead

Week of 8/26/22- This week the sewer line to the Event Center is complete and all of the under slab plumbing is completed and the foundation is completed and ready for the erection of the building which will occur on August 30th. We have a targeted date for moving the fire equipment into the building by 2/15/2023 for approximately 10 to 12 months while the main station is built.

Overhead Site  Event Center Steel Staging Event Center Steel Staging

 

Week of 7/11/22- This week we recieved more materials and began grading for the Temporary fire station / events center.

Overhead Site Events Center site prep grading

rebar  underground pipe

Week of 6/13/22- Construction Began with the installation of the Erosion and Sediment Control and obtaining our Grading permit on June 9, 2022. The stage was removed and the prepping of the site pad for the new Event Center began. The Events Center will serve as a temporary fire house while the new one is built.

Stage Removal  Stripping Site overview 6/10/22

   

 

May 4, 2022- Construction trailer and fencing arrive

April 18, 2022- Steel arrives for the temporary building / future events center

 

April 4, 2022- Ground Breaking Ceremony was held to kick off the beginning of our multi-year building projects

 

Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
Hampstead Volunteer Fire Engine &
Hose Company No. 1

1341 North Main Street
P.O. Box 231
Hampstead, Maryland 21074
Emergency Dial 911
Station 2 Voice: 410-239-4280
Station 2 Activities: 410-374-2424
Station 2 Fax: 410-239-0523
E-mail: info@hampsteadvfd.org
Copyright © 2024 Firehouse Solutions (A Service of Technology Reflections, Inc.)